Carrier Chiller Installation September 2005Chiller installation for Carrier Chillers this was the installation of one 800Kw and one 500Kw chillers used to provide chilled water for the Printing Presses, and also for the factory air conditioning total cost of the equipment £130,000 Harris M600 Lithographic Press Installation Heidelberg New factory for Quebecor World October 2004 - Moore Electrical was the principle contractor for the Electrical installation.
Megtec Enterprise Afterburner New Regenerative Afterburner state of the art pollution control required for many industries to comply with the Governments 1990 Environmental Protection Act.
|
|